The exact timeline is still in the planning stages, but preliminary plans are as follows.
- Road change would start immediately
- Performing arts center (estimated December 2021 completion).
- Benton and Middle School storm shelters likely the start of school August 2021.
- Field and Central shelters before the end of 2020.
- Athletic venues would be phased with other projects (i.e. – existing locker room upgrades would happen relatively quickly; however, new locker rooms would probably have to wait until band/choir had new spaces).
- Baseball field would have to be built at the sports complex near the jr high before the end zone practice and community facility could be started.