Project Timeline

The exact timeline is still in the planning stages, but preliminary plans are as follows.

  • Road change would start immediately

  • Performing arts center (estimated December 2021 completion).

  • Benton and Middle School storm shelters likely the start of school August 2021.

  • Field and Central shelters before the end of 2020.

  • Athletic venues would be phased with other projects (i.e. – existing locker room upgrades would happen relatively quickly; however, new locker rooms would probably have to wait until band/choir had new spaces).

  • Baseball field would have to be built at the sports complex near the jr high before the end zone practice and community facility could be started.